Donegal Drive Culvert Improvements

Brandstetter Carroll Inc was hired by Sycamore Township to design the improvements to Donegal Drive Culvert Improvements.

The culvert is located at the intersection of Gwilada Drive and Donegal Drive.  The improvements will consist of modifications to the outlet end of the existing headwall, construction of new wingwalls and grading work.  The plans will be completed by June and the construction scheduled for this Summer.


Dillonvale Culvert Improvements

Carpenter Marty Transportation will be doing land surveying work this week and into early next week at the following locations:

3946 & 3945 Mantell Avenue

3904 & 3905 Mantell Avenue

8589 & 8596 Wicklow Avenue

This land survey work is being performed to gather data on the existing culverts to prepare improvement plans.  The improvements will consist of modifications to the existing headwalls, construction of new headwalls and grading work.  The plans will be completed by June and the construction is scheduled for this Summer.